2012-11-26 - 5422 - Break Fix - Wrong Factory Calendar #US #Calendar #MMPPSupport #SDSupportRoutes

5422.200 - Wrong Factory Calendar

Summary Description


The Requested delivery date is pushed to future (12/03/2012), even though stock is existing.

Admin Info



Title
5422.200 - Wrong Factory Calender
Requested by
Thi Tran
Issue Date
11-23-2012
Resolved by
Adithya & Surya
Resolved Date
11-28-2012
Status
Complete

Detailed Description

(Include Screen Shots if required )

For the following Sales Order, the requested delivery dates in schedule line level are pushed to 12/03/2012 even though the stock is existing.

Analysis and Recommendations

(Include Screen Shots if required)

It was observed that the issue was with the Route that is used in the sales order.
The Route WEWWTR is been used and it is observed that for that Route Z1 calender is used.
Route_Z1_calender.png

Transit time of 1 day and calender Z1 is maintained for Route WEWWTR.

It is observed that the calender Z1 is having Plant Shutdown from 11/22/2012 to 12/02/2012.

Route_Z1_Assign.png
So in our present sales order "1303749" the requested delivery date is 11/28/2012. Even though there is enough stock, by considering the transit time of one day and by considering the plant shut down time
(from 11/22/2012 to 12/02/2012 holidays) system has proposed 12/03/2012 as delivery date.
We need to maintain the correct assignment of calender to the Route.

Resolution


Updated the routes by assigning the corresponding suitable calenders.
Update Routes.xlsx